The data center power revolt is mostly a press release. Bloomberg’s reporting, drawing on Cleanview and BNEF figures, shows about 165 gigawatts of announced gas generation co-located with US data centers against roughly 2 gigawatts actually operating as of June, while 58 gigawatts of capacity sits under construction. The economics explain the gap: on-site gas runs above $100 per megawatt-hour versus about $90 for grid power, turbines now take five-plus years to arrive, and single-site plants lack grid redundancy against AI loads that swing within seconds. Evercore ISI puts average grid-connection waits near four years, stretching to ten. So developers build their own plants as a bridge, buying speed and control, not cheaper electrons.